26 June 2015 |
Boroondara Sport & Recreation Strategy > data / survey submitted to Council – exactly the same needs re courts / lights as current |
11 April 2016 |
Sport & Rec Strategy endorsed by Council, identifying that “netball was experiencing a high growth in demand and would required additional access to facilities in the future” |
14 April 2016 |
Email + petition from Mont Albert Netball Club to Council regarding lack of lighting & safety issues > advised that it would be addressed in the MMMP |
8 May 2017 |
Myrtle Macleay Park Management Plan (MMPMP) consultation commenced = managing growth at Macleay/Myrtle > Boroondara Netball Centre
|
2017 |
The Statewide Facilities Strategy released by the State Government identifying the City of Boroondara as lacking appropriate facilities to cater for netball participation & growth in the area stating the significant need for outdoor, lit courts in Boroondara.
|
14 Feb 2018 |
Netball Victoria advises BNA that BNC is a Netball Vic Priority Project |
23 Feb 2018 |
Email to Council from BNA > Netball Vic’s Eastern Metro Zone Profile / request for council action |
17 April 2018 |
Meeting BNA & Council Officers > discussion about issues, need for additional courts
|
18 August 2018 |
Meeting PWG > urgent need for facility expansion discussed again
|
29 August 2018 |
BNA & NV > Formal Project Brief commenced as requested |
26 February 2019 |
Meeting PWG > discussion re demand analysis, gap analysis > information required |
April 2019 |
State of Play Report released = data prepared by Sport Australia providing accurate information on trends in netball participation & opportunities to maximise participation & engagement. |
26 April 2019 |
Media Release from Josh Frydenberg > $1.2 million for 4 additional netball courts – election commitment |
27 April 2019 |
Public announcement at BNC by Josh Frydenberg > Election commitment to fund 4 additional netball courts after discussions with CEO |
June 4 & 18, 2019 |
2x PWG meetings cancelled |
July 3 2019 |
BNA submission of data > Data & Findings document incl. Schedule of Usage, current & desired |
24 July 2019 |
Email to Council Officers > request for response and next meeting |
1 August 2019 |
Email to Councillors, CEO, Council Officers > request for feedback; any progress since our submission? |
2 August 2019 |
Change of Council Officers |
6 August 2019 |
Request to new Council Officers for a meeting (deferred since June 4) as no feedback received
|
16 August 2019 |
Email from Jane Addis (current Mayor) > apparently not aware of data submitted by PWG. |
17 Sept 2019 |
Meeting PWG to discuss findings, next steps & timeline |
7 Nov 2019 |
Request from Government Dept Health re status of the Government grant |
8 Nov 2019 |
Advised by Council Officer that this project is a priority / working towards resourcing a master plan for the whole Macleay Park site |
20 Nov 2019 |
Council Officers to present the State of Play report to Council > no correspondence received |
3 Feb 2020 |
Meeting with Council Officers & Mayor (Cynthia Watson) – Mayor did not attend
|
19 April 2020 |
Request from Government Dept Health re status of grant
|
7 May 2020 |
Request from Government re status of grant |
10 June 2020 |
Request from Council to support their application for a Community Sports Infrastructure Grant for a 2 court stadium at Fritsch Holzer Reserve > request DENIED as no consultation with BNA or NV |
19 July 2020 |
Email from Phillip Storer (CEO) advising that they were hoping to use our funds to build 4 outdoor courts at Fritz Holtzer Reserve, an option we should welcome. Once again, no consultation with BNA. |
20 July 2020 |
Email from BNA to CEO advising that the funding was for BNA specifically and not Council |
3 August 2020 |
Email to BNA from Netball Victoria CEO (Rosie King) advising their disappointment with the lack of transparency and process within Council |
7 August 2020 |
Netball Victoria phone meeting with Council officer about lack of facilities in this LGA
|
2 Sept 2020 |
Letter sent to all Councillors from BNA outlining our concerns with the complete lack of transparency, process & communication undertaken by Council on this issue (see Letter to Council) |
22 Sept 2020 |
Response from Mayor (Cynthia Watson) which did not reflect knowledge of the data & information provided to Council by the PWG
|
24 Sept 2020 |
Letter from BNA to Council Officers requesting “clarification on some of the extraordinary comments made by the Mayor” |
5 October 2020 |
Questionnaire sent to all aspiring Councillors to raise awareness of BNA and to gauge their support |
6 October 2020 |
Newsletter disseminated to 3800 BNA members advising them to defer voting until we can forward a list of our preferred “netball friendly” candidates. |
8 Oct 2020 |
Response from Council Officers advising of Council’s recent “organisational redesign”.
|